Sani Usman Kukasheka: Wither the reconstruction of Abuja-Kaduna-Zaria-Kano road project

Final week, I got here throughout a message by WhatsApp in regards to the gradual progress of the rehabilitation of the Abuja-Kaduna-Zaria -Kano street. I needed to dismiss it as a kind of politically motivated mischiefs straddling the social media each day. Nonetheless, I noticed it in so many different platforms, attributing to a member of the nationwide meeting on oversight operate. I’ve to pay extra consideration, given the significance hooked up to the street and it’s rehabilitation. There isn’t any doubt, it is without doubt one of the most annoying items of data flying round concerning that street. The report was an evaluation by the Chairman Home Committee on roads lamenting on the speed of progress.

In keeping with a web-based newspaper, Premium Instances of twenty ninth August 2020, “The Home of Representatives has expressed fear over the gradual tempo of labor on the Abuja-Kaduna-Zaria-Kano roads initiatives awarded by the Federal Authorities in 2018. The Chairman, Home Committee on Works, Kabir Abubakar Bichi, ‎disclosed throughout a courtesy go to to Governor Abdullahi Ganduje on Friday in Kano.”

The medium additional acknowledged that Kabir Bichi mentioned, “We’re disenchanted that after about 26 months because the graduation of labor on the mission, solely lower than 20 per cent of the work achieved.‎ Regardless of gathering N70 billion out of the N155 billion complete sum of the contract, Berger remains to be but to do substantial work on the initiatives, and the contract tenure is 36 months. The corporate spent 26 months on the mission, they usually have solely 9 months remaining. In part one of many mission, from Zuba to Kaduna, sadly, solely 10 km ‎has been executed out of the 165 km. As compared, from Kaduna to Zaria solely 5 to 6 km accomplished out of the 75 km, then from Zaria to Kano ‎the one 11 km executed.” He additionally threatened that “the Home is not going to settle for any extension of the completion date or a variation of the mission.” The lawmaker’s indignation is a sentiment shared by all well-meaning individuals within the 12 states of the North. Why the gradual charge of progress is a query that begs for a solution. This anomaly can solely be unraveled by a public listening to and asking the proper individuals, significantly these accountable within the supervising ministry this query. The individuals, particularly the northerners, have each proper to be involved with the gradual part of the work because it impacts them most.

🎴Read Also▶️
BREAKING: Lagos Lawmaker, Tunde Buraimoh, dies

Furthermore, it there may be credible data that the work was duly paid for by the Federal Authorities and given to the most effective building firms within the nation, Julius Berger Nigeria PLC. So, what went mistaken? Is it sabotage or what? In that case, by who and why?

There isn’t any doubt the twin carriageway that connects most northern elements of the nation and past is the Abuja-Kaduna-Zaria-Kano. Julius Berger Nigeria PLC additionally acknowledged that “The Abuja-Kaduna-Zaria-Kano Highway varieties a vital a part of this bigger freeway system, enabling the motion of individuals and merchandise from the North to the South and vice versa – thereby uniting the Nigerian individuals and financial system, and connecting Nigeria to North Africa through the Lagos-Algiers Trans-African Freeway.” It’s on this regard that the Buhari administration determined to rehabilitate it following the closure of Nnamdi Azikiwe Worldwide Airport for upkeep and the truth that the freeway has develop into a loss of life entice filled with potholes. The felony bandits make the most of its state of disrepair, to rob and abduct individuals—the variety of street site visitors accidents that claimed so many lives can also be unprecedented.

🎴Read Also▶️
Abuja: FCTA blames shanty towns for insecurity

Earlier than I’m going additional, I wish to acquaint you with the background to the street mission. It was contracted by the self-styled navy President Ibrahim Badamasi Babangida’s authorities within the Eighties. It is without doubt one of the most important strategic street networks within the North and certainly the nation because it hyperlinks numerous elements of the Nigeria and past. The contractor, Julius Berger Nigeria PLC, denoted the significance of the street when it acknowledged that “Certainly one of Nigeria’s most necessary highways runs from North to South. The Abuja-Kaduna-Zaria-Kano Highway varieties a vital a part of this bigger freeway system, enabling the motion of individuals and merchandise from the North to the South and vice versa – thereby uniting the Nigerian individuals and financial system, and connecting Nigeria to North Africa through the Lagos-Algiers Trans-African Freeway.” On condition that, and lots of different causes, the Buhari lead Federal Authorities contracted Julius Berger Nigeria PLC to rehabilitate and reconstruct the 375.9 km Twin Carriageway, which stem from the Federal Capital Territory, Abuja by Kaduna, Zaria and to Kano, utilizing asphalt recycling methodology, greater than two years in the past.

Sadly sufficient, a little bit over two years into the contract, nothing vital could possibly be seen on the street’s rehabilitation. In keeping with the lawmakers, and solely a little bit distance of the street is accomplished. Thus, aggravating the struggling of commuters and the residents of these states.

So much has been mentioned in regards to the gradual progress of the street, citing lack of funds as the principle difficulty.

Opposite to those speculations, the gradual progress of the work is usually as a consequence of egocentric causes and lack of will to oversee the mission by these accountable. This has given option to the unlucky blame recreation and most significantly, casting the President in a nasty gentle. I hate to say, however there some parts of sabotage by some but to be recognized individuals. Rightly or wrongly, the President has the accountability to make sure that these he entrusted with the work do it diligently and to his satisfaction. Extra so, from the start, it was reliably gathered that some individuals in authorities should not proud of the reconstruction work and vehemently opposed the award of contract, citing lack of funds. It took the intervention of the then Chief of Workers to the President, late Alhaji Abba Kyari, to name their bluff, together with the intent of giving the work to 5 completely different contractors in piecemeal. He additionally argued that the job if given to varied contractors, would have an effect on its high quality. He stood his floor and was backed by the President, thus, the work was awarded to Julius Berger PLC. Everybody is aware of that sufficient budgetary provision was made for and arguably absolutely paid for, and the corporate can ship, however the nagging query is why the work has not been transferring on the required velocity, thus inconveniencing commuters and risking the lives of motorists that ply the street each day?

🎴Read Also▶️
Ooni provides stranded Nigerians hope

Subsequently, the renewed involved by the lawmakers is a step in the proper path, and they need to not draw back from summoning Julius Berger PLC, the Ministers of Works and Housing and his Finance counterpart to clarify why the mission goes at snail velocity. The general public desires to know.

The author, Sani Usman Kukasheka, mni, is Abuja based mostly Public Relations marketing consultant and may be reached on his twitter deal with @skusman.

About Hotgist

Check Also

Buhari hosts Sultan of Sokoto says his govt wont tolerate - Buhari hosts Sultan of Sokoto, says his govt won't tolerate ethnic, religious prejudice

Buhari hosts Sultan of Sokoto, says his govt won’t tolerate ethnic, religious prejudice

President Muhammadu Buhari on Thursday warned that stoking ethnic and non secular prejudices won’t augur …

Leave a Reply

Your email address will not be published. Required fields are marked *